2 FT — The build

Nine stages. Each one has a week, a payment and a job for you.

This is how a Saltbrook pool gets built, in order. Pick your swim month below and the schedule works itself out backwards.

When do you want to swim?
Sign by Sat, Jan 23, 2027 to swim in May 2027.Plan my build →
Stage 5 of 9ShellMar 13 – Mar 20 · 1 week
Payment at this stage25% of contract
What we need from youWater the new shell twice a day for a week.
A typical schedule, not a promise. Permits and weather move dates. We confirm yours after a site visit.

3 FT — The job binder

Every stage gets its own page. You sign off one before we turn to the next.

Scroll through the binder your project lead brings to every site meeting: what happens, what we need from you, and what’s due.

1

FT

Design and 3D plan

2 weeks

10% deposit

What happens

We measure the yard, check access and draw the pool in 3D with your finishes, equipment and a fixed price.

What you do

Approve the layout, the finishes and the equipment list.

Design and 3D plan

2

FT

Permits and HOA

3 weeks

Nothing due

What happens

We file engineering and drawings with the city and prepare your HOA packet.

What you do

Sign the HOA form and tell your neighbours when we’ll dig.

Permits and HOA

3

FT

Dig and forms

1 week

20%

What happens

The excavator shapes the pool. Soil leaves the same week, and forms set the shape of the shell.

What you do

Clear a path to the yard and keep pets inside on dig day.

Dig and forms

4

FT

Steel and plumbing

1 week

Nothing due

What happens

Rebar cage, main drains, returns and lighting conduit go in. The city inspects before anything is poured.

What you do

Nothing. We send photos of the inspection.

Steel and plumbing

5

FT

Shell

1 week

25%

What happens

The concrete shell is sprayed in one day and starts to cure.

What you do

Water the new shell twice a day for seven days.

Shell

6

FT

Tile and coping

2 weeks

15%

What happens

Waterline tile and coping stones are set and grouted.

What you do

Confirm your tile on site before we set the first piece.

Tile and coping

7

FT

Deck and electrical

2 weeks

15%

What happens

Decking is poured or laid, and equipment is wired to the panel.

What you do

Walk the deck layout with us and confirm where furniture goes.

Deck and electrical

8

FT

Finish and fill

1 week

15%

What happens

The interior finish goes on and the pool fills without stopping.

What you do

Leave the hose running. No swimming yet.

Finish and fill

9

FT

Start-up and handover

1 week

Nothing due

What happens

We balance the water, start the equipment and walk you through it.

What you do

Pool school: an hour with us learning every control.